The Ghana Grid Company (GRIDCo) has announced the full restoration of power supply nationwide following a transmission system disturbance that disrupted electricity in several parts of the country on the night of Thursday, April 3, 2025.
The incident occurred at approximately 8:09 PM, when the Tafo-Nkawkaw transmission line tripped due to a fault. Efforts were immediately undertaken to restore the line; however, in the process, several adjacent lines also tripped, triggering the shutdown of key power plants.
This cascade of events led to a significant dip in generation, causing power outages in parts of Accra, Kumasi, Sunyani, Techiman, Bui, Tumu, Sawla, and other areas across northern Ghana beyond Kumasi.
GRIDCo’s System Control Centre (SCC) acted swiftly to stabilize the national grid and initiate a phased restoration process.
Through the coordinated efforts of the control team, power supply to the affected regions was fully restored by 10:57 PM, less than three hours after the disturbance.
In an official statement released on Friday, GRIDCo expressed regret over the inconvenience caused by the outage and extended its apologies to the general public, assuring citizens of its continued commitment to delivering reliable and stable power supply across the country.