The Tema Oil Refinery (TOR) has successfully resumed crude oil refining operations after several years of inactivity, marking a major milestone in the revival of Ghana’s downstream petroleum sector.
The resumption follows the completion of extensive Turnaround Maintenance (TAM) works on the refinery’s Crude Distillation Unit (CDU), carried out between 1 August and 30 October 2025 in line with international engineering, safety, and operational standards.
After the maintenance works, the National Petroleum Authority (NPA) conducted regulatory inspections and confirmed TOR’s full compliance with all safety and operational requirements, granting clearance for refining activities to resume.
TOR will operate on a phased basis in the coming months to stabilize systems and optimize performance ahead of its official recommissioning.
As part of its upgrade programme, the refinery has installed a new furnace, F-61, which will soon be commissioned and integrated into the CDU. The upgrade is expected to restore TOR’s original capacity of 45,000 barrels per stream day from the current 28,000 bpsd, with plans to expand to 60,000 bpsd in the medium term.
The Government of Ghana is expected to formally commission the new furnace at a later date.
TOR expressed appreciation to President John Dramani Mahama, the Minister for Energy and Green Transition, Dr. John Abdulai Jinapor, and other stakeholders for their support, while reaffirming its commitment to safe, efficient, and sustainable operations.