The Ghana Grid Company Limited (GRIDCo) has completed the initial phase of repair works on the Ashaiman section of the 161kV Tema–Achimota transmission line.
GRIDCo said its engineers carried out preliminary works on Sunday, August 16, 2026, following damage to a transmission tower caused by a welding explosion in July.
The company confirmed that power has since been restored to affected customers.
However, GRIDCo said the remaining work, involving the replacement of the damaged transmission tower, will be undertaken on Sunday, August 23, 2026.
GRIDCo, in collaboration with the Electricity Company of Ghana (ECG), said it will provide advance information to customers and communities that may be affected by the planned works, including any associated power interruptions.
The company said the work is intended to restore the full integrity, reliability and resilience of the transmission line.