Rosemond Owusu-Duah
Rosemond, Electrical Supervisor at our Tarkwa crushing plant, who has been part of our team for 13 years. Rosemond joined us for her national service and has been building her career with us since then.
Rosemond’s list of career highlights (so far) illustrates that mining is never boring. She has been involved in various initiatives related to energy, tailings and water conservation that have resulted in business improvements.
“The opportunities and experiences I have had working in past and current sections and projects at Gold Fields have expanded my knowledge and experience in engineering and strategic management,” she says.
“The satisfaction of solving engineering problems and collaborating with various departments and people to achieve our goals motivates me.”
About Rosemond Owusu-Duah
I started working in the Goldfields Ghana Limited as a National Service Personnel with Learning and Development Department as the Engineering Training Officer in 2010.
She worked as a Training Officer officially after my NSS period from September 2011 until I joined the Engineering team in 2015 where I was the Frontline coach for Engineering with the Business Improvement Department.
In 2016, She was one of the team of engineers assigned to supervise and spearhead the construction of the Genser Power Plant and the initial three (3) Solar Mars Turbines installation.
She was later moved to join the instrumentation crew at the crushing section in 2017 to 2018 where I gained valuable skills in systems control and instrumentations. I am currently the Electrical supervisor for the crushing plant, a position I have held from April 2018 to date.
Achievements
The installation and construction of the initial 30MW Genser Power Plant by the engineering team of which I was included reduced the power cost $/kwhr the company incurred. This plant still provides a constant alternative power supply when the national grip is off.
Contributed to the reduction of power factor from 0.94 to 0.96 by saving the company the surcharges of US$557,153 from power distribution company by installations of two (2) of 1650kvar capacitor banks within the medium voltage circuit.
Involved in the construction of 11kv power line to the mine village to enhance power supply and availability. This resulted into a cost reduction of US$90,119 to the mine.
Supervised my crew and assisted with the dam raise for the Tailings Storage Facility (TSF02) to increase the dam capacity. Worked along with the Metallurgical department crew both day and night extensively to expand the dam capacity from 8.2milliontons to 14.2milliontons.
Assisted with the installation of the clarifier 500+ which has helped to reduce the TSF supernatant water to <20% and increase water supply to the CIL and treated the processed water for both storage and re-use by 150%.