Director of Public Affairs at Ghana Gas, Ernest Owusu Bempah, has said the Nana Akufo-Addo administration has so far paid $3.6 billion in the past seven years for the ENI/Sankofa gas pipeline deal signed by the Mahama administration in 2015.
Ernest Owusu Bempah was briefing Journalists in Accra on Tuesday, November 1 about how the contract which he termed as the ‘most expensive gas contract in the world’.
On a monthly basis, he explained, Ghana is paying $46 million, making it $552 million yearly.
This contract, he intimated, was also signed for 20 to 25 years.
“The Akufo-Addo government had no choice but to continue with the contract when it came into office because of the terms and conditions.”
“This contract was signed for 20 to 25 years, monopoly for that period and the IMF questioned it.”
“We wouldn’t be going to the IMF but for some of these reckless dubious contracts signed by the Mahama administration,” he explained.
According to Ernest Owusu Bempah the contract is partly to blame for the current economic challenges facing the country.
The government is unable to reduce cost of electricity for thermal generation,” he stressed.
Former President Mahama signed the agreement with ENI and Vitol Energy at a ceremony at the Peduase lodge near Aburi in 2015.
This was, at the time, probably the biggest single largest foreign direct investment in West Africa and indeed Ghana since independence.
The project was situated in the Western region.
The oil production from the offshore cape three points was estimated at eighty thousand barrels per day.